Power engineering projects in the field of High Voltage
Reconstruction of 110 kV overhead line in Cracow, connecting Cracow agglomeration with Elektrociepłownia Skawina under the communication project including the control and supervision system executed by ZUE S.A. The value of the project amounted 150 million PLN. The scope of works associated with the reconstruction of this line comprised of:
  •     Dismantling of the old lines and poles
  •     Installation of foundations for tubular poles using the piling technology
  •     Installation of pass-through and robust tubular poles including insulation fittings
  •     Tightening works including mounting of AACSR/AW SS-72F 150/30 ASLH-D(S)bb 2x48 SMF lightning arrester wire and AFL-8 525 mm working wires

Implementation of reconstruction project of introduction of L-248 line to the modernized Braniborska station (in Zielona Góra locality);
 
Development of the concept of replacing 110 kV overhead line from Janów to Radogoszcz with the cable line including the development of technical and economic analysis;
 
The acquisition of the rights to land (for construction purposes including obtaining the transmission easement) for the planned investment of 110 kV line S-458 within the below project: “Construction of 110 kV overhead line [S-458] (from 220/110 kV Polkowice station to pole No. 54 of the existing S-452 line.”

 